Progress Through - 23 February, 2009
Grass Planting Strip along Driveway
(February 23, 2009)
Grass Planting Strip along Driveway
(February 23, 2009)
Still Waiting for 3 Tiki Torches at Driveway
(February 23, 2009)
Grass Pavers
(February 23, 2009)
Added Security Equipment Panel
(February 23, 2009)
Reinforce Washout Area Along Driveway to Cottage
(February 23, 2009)
Palapa Cedar Ceiling
(February 23, 2009)
Palapa Cedar Ceiling
(February 23, 2009)
Palapa Cedar Ceiling
(February 23, 2009)
Cottage Lower Lawn
(February 23, 2009)
Septic Tank Access at Cottage Lawn
(February 23, 2009)
A/C Installed Behind Cottage
(February 23, 2009)
Garage Shelving not yet Painted
(February 23, 2009)
Painted Garage Shelving with Landscape Lighting Transformers Below
(February 23, 2009)
Equipment Wiring still in progress at Media Room
(February 23, 2009)
Equipment Wiring still in progress at Media Room
(February 23, 2009)
Courtyard
(February 23, 2009)
South Railing Installed (Still Needs Color)
(February 23, 2009)
South Railing Installed (Still Needs Color)
(February 23, 2009)
North Railing with Color
(February 23, 2009)
Palapa Shower Railing
(February 23, 2009)
Palapa
(February 23, 2009)
Pool Deck Tree - Bamboo Screen at Master Bed Getting Taller
(February 23, 2009)
BBQ Area
(February 23, 2009)
Plants Growing In at Gym - Much Better Landscape Screening from Road and Driveway
(February 23, 2009)
Grading Uphill of Gate
(February 12, 2009)
Preparing Lawn Strip by Driveway
(February 12, 2009)
Grading Downhill of Gate
(February 12, 2009)
Porte Couchere
(February 12, 2009)
Garage
(February 12, 2009)
Palapa Roof
(February 12, 2009)
Cottage Kitchenette
(February 9, 2009)
Cottage Bed Closet
(February 9, 2009)
Cottage Bath 1
(February 9, 2009)
Cottage Bath 2
(February 9, 2009)
A/V Wiring
(February 9, 2009)
Battery Backup Added to Security System (3 places)
(February 9, 2009)
Lanai Doors
(February 9, 2009)
Dining Area
(February 9, 2009)
Teak Doors for Palapa
(February 9, 2009)
Palapa Ceiling
(February 4, 2009)
Palapa Ceiling
(February 4, 2009)
Palapa - 8 Recessed Ceiling Fixtures
Center Section still needs 8 sided Flat Area Framed
(January 28, 2009)
Palapa - Data and Power Jack 1 of 2 columns (at end of doors)
(January 28, 2009)
Palapa - Data and Power Jack 2 of 2 columns (at end of doors)
(January 28, 2009)
Palapa - Light Switch on Column in Between Doors
(January 28, 2009)
Palapa
(January 28, 2009)
Palapa - Stocking Roofing
(January 28, 2009)
Spa Deck
(January 28, 2009)
Pool Deck from Master Lawn
(January 28, 2009)
Art Glass Installed at Cottage Baths
(January 12, 2009)
Art Glass Installed at Bath 4
(January 12, 2009)
Shoe Rack in Garage
(January 12, 2009)
Shoe Rack in Garage
(January 12, 2009)
Previous photos
as of December 18, 2008
as of October 30, 2008
as of September 30, 2008
as of August 28, 2008
as of July 31, 2008
as of June 30, 2008
as of May 23, 2008
as of April 28, 2008
as of March 6, 2008
as of February 26, 2008
as of January 25, 2008
as of December 15, 2007
as of November 28, 2007
as of October 30, 2007
as of September 28, 2007
as of August 30, 2007
as of July 23, 2007
as of June 29, 2007
as of May 24, 2007
as of April 23, 2007
as of March 29, 2007
as of February 27, 2007
as of December 26, 2006
as of November 30, 2006
as of October 31, 2006
as of September 29, 2006
as of September 12, 2006
as of June 1, 2006
as of April 26, 2006
Design Board Story Pole - September 12, 2005