Dixon Homes, Inc.
our home page
Residence
Progress Through - 25 January, 2008
Top of Artwork is Not Visable When Standing on Courtyard Lawn
(January 25, 2008)
Most Will Be on Walkway when Passing Artwork
When you are this close artwork is nicely centered
(January 25, 2008)
Inside the Hallway
The two boards on the ground are 11" high for reference, the actual baseboard is only 9" high
(January 25, 2008)
Stucco Rock Cap Detail - No foam
(January 25, 2008)
Stucco Rock Cap Detail
(January 25, 2008)
Courtyard
(January 24, 2008)
Rockwork Behind Waterfall at Porte Couchere
(January 24, 2008)
Dry Stream Bed
(January 24, 2008)
Waterfall
(January 24, 2008)
Stream Bed
(January 24, 2008)
Sidewalk
(January 24, 2008)
Kitchen
(January 24, 2008)
Kitchen
(January 24, 2008)
Kitchen
(January 24, 2008)
Powder Room by Media Room
(January 24, 2008)
Bath 2 Shower
(January 24, 2008)
Bath 2 Shower
(January 24, 2008)
Master Bedroom Window Blind Prep at Curved Window
(January 24, 2008)
Her Master Vanity
(January 24, 2008)
Master Shower and Bench
(January 24, 2008)
Master Closet
(January 24, 2008)
Large Utility Room
(January 24, 2008)
Porte Couchere Concrete
(January 24, 2008)
Lower Hillside
(January 24, 2008)
Tree by Media Room
(January 24, 2008)
Pool Equipment Area
(January 24, 2008)
Stucco Prep - Plastic Lumber and Concrete for Curved Cap Detail
(January 24, 2008)
Stucco Prep
(January 24, 2008)
Stucco Prep - Before Scratch Coat
(January 24, 2008)
Stucco Prep - Scratch Coat inside Plastic Lumber
(January 24, 2008)
Office Cabinets
(January 21, 2008)
Office Cabinets
(January 21, 2008)
Media Room - Art Wall Cabinet Behind Seating Area
(January 21, 2008)
Media Room - Monitor Wall Cabinets in Progress
(January 21, 2008)
Powder Room Across from Pantry
(January 21, 2008)
Pantry (low light dark, fuzzy photo)
(January 21, 2008)
Bath 2 Shower Tile
(January 16, 2008)
Bath 2 Shower Floor Prep
(January 16, 2008)
Hallway Art Area
(January 16, 2008)
North Art Wall
(January 16, 2008)
Window Blind Pocket at Curved Door
(January 16, 2008)
Lower Hillside Planting
(January 16, 2008)
Plater Area By Pool Stairs
(January 16, 2008)
Upper Planter Area
(January 16, 2008)
Main Electrical Service Wire Installed
(January 16, 2008)
Data and Telephone Wiring Area
(January 16, 2008)
Enlarged Trench to Gulley Directly Above the Washout Area by Garage Below
(January 16, 2008)
Cleaned Out Trench Next to Berm Above Property Line
Gravel to the Right in Photo was Existing Berm
(January 16, 2008)
Eliminated Hump In Berm that Allowed Water to Accumulate and Folw by Porte Cochere
(January 16, 2008)
House Below
(January 16, 2008)
Spread Out Soil and Knocked down Weeds on Lot
(January 16, 2008)
Spread Out Soil and Knocked down Weeds on Lot
(January 16, 2008)
Master Shower
(January 7, 2008)
Master Shower
(January 7, 2008)
Large Utility Room
(January 7, 2008)
Large Utility Room
(January 7, 2008)
Kitchen Counter Templates
(January 7, 2008)
Lower Hillside Planting in Progress
(January 3, 2008)
Lower Hillside
(January 3, 2008)
Master Lanai
(January 3, 2008)
Master Lawn Area and Palapa Area below
(January 3, 2008)
Palapa Area and Cottage Below
(January 3, 2008)
Pool Deck
(January 3, 2008)
Kitchen
(January 3, 2008)
South Art Wall in Living Room
(January 3, 2008)
Courtyard
(January 3, 2008)
Previous photos
as of December 15, 2007
as of November 28, 2007
as of October 30, 2007
as of September 28, 2007
as of August 30, 2007
as of July 23, 2007
as of June 29, 2007
as of May 24, 2007
as of April 23, 2007
as of March 29, 2007
as of February 27, 2007
as of December 26, 2006
as of November 30, 2006
as of October 31, 2006
as of September 29, 2006
as of September 12, 2006
as of June 1, 2006
as of April 26, 2006
Design Board Story Pole - September 12, 2005