Residence
Progress Through - 23 April, 2007



Roof Framing over Kitchen
(April 23, 2007)


Roof Framing over Living Room
(April 23, 2007)


Kitchen Roof
(April 23, 2007)


Living Roof
(April 23, 2007)


Roof from Lower Hillside
(April 23, 2007)


Looking North from Living Room
(April 23, 2007)


Upper Hillside from Kitchen Window
(April 23, 2007)


Rocks for Courtyard Waterfeature
(April 23, 2007)


Rocks for Courtyard Waterfeature
(April 23, 2007)


Upper Planter Bench Wall
(April 23, 2007)


Pool Equipment Floor Poured
(April 23, 2007)


Spa Equipment Lines
(April 23, 2007)


Pool Equipment Room
(April 23, 2007)


Gym
(April 23, 2007)


Roofing over Dining Bay / Living Room
(April 23, 2007)


Lower Cottage Wall
(April 23, 2007)


Lower Cottage Wall - Looking up to Main House
(April 23, 2007)


Foundation Prep at Cottage
(April 23, 2007)


Curved Stair Retaining Walls
(April 23, 2007)


A/C Units in Guest Bedroom Ceiling Wing
(April 23, 2007)


Waterfeature Model - View from Stairs Between Porte Couchere and Gym
(April 23, 2007)


Waterfeature Model - View from Breakfast Bay
(April 23, 2007)


Waterfeature Model - Closeup of Falls
(April 23, 2007)


Waterfeature Model - Overhead - Kitchen Bay Lower Right
(April 23, 2007)


Waterfeature Model - Overhead - Rotated 180 Degrees and Further out
(April 23, 2007)


Zoom In from Above
(April 16, 2007)


Setting Skylights at Porte Couchere
(April 16, 2007)


Setting Skylights at Porte Couchere
(April 16, 2007)


Kitchen Windows to Courtyard
(April 16, 2007)


Kitchen Windows to Courtyard
(April 16, 2007)


Close up of Typical Large Rafter Hold Down Welded to Steel Beam
(April 16, 2007)


Close up of Upper Steel Brackets
(April 16, 2007)


Welded Connection at Ridge
(we will paint after special inspection has been completed on this weld)
(April 16, 2007)


Another Ridge Connection
(April 16, 2007)


Electrical Service Area new Temp Power Pole Set
(April 16, 2007)


Cottage Formwork and Copper Waterline from Above in Foreground
(April 16, 2007)


Cottage Formwork
(April 16, 2007)


Lower Cottage Wall
(April 16, 2007)


Conical Roof
(April 12, 2007)


Close-up of Center of Conical Roof Steel
(April 12, 2007)


Post Installed above Concrete Column - South Side
(April 12, 2007)


Post Installed above Concrete Column - North Side
(April 12, 2007)


Post Installed above Concrete Column - North Side (different angle)
(April 12, 2007)


Roof Framing
(April 12, 2007)


Living Room
(April 12, 2007)


Roof Framing
(April 12, 2007)


Bed 4
(April 12, 2007)


Ceiling Above Master Closet
(April 12, 2007)


Ceiling Above Master Closet
(April 12, 2007)


Master Bed Soffit Contech Fixtures
(April 12, 2007)


Office - Duct at Right Should be Moved to Left
(April 12, 2007)


Hall from Office to Living Area
(April 12, 2007)


Conical Roof Framing
(April 10, 2007)


Living Room
(April 10, 2007)


Living Room
(April 10, 2007)


Lifting Large Rafters
(April 10, 2007)


Pool Equipment
(April 10, 2007)


Lower Hillside Looking West
(April 10, 2007)


Lower Hillside Looking Northeast
(April 10, 2007)


Main Electrical Underground Service Install in Progress
(April 10, 2007)


Erecting Center Roof
(April 9, 2007)


Jute Fabric Re-Installed over Topsoil
(April 9, 2007)


Entry Drive
(April 9, 2007)


Center Roof Framing
(April 9, 2007)


Upper Pool Deck Landscape Wall
(April 9, 2007)


Pool / Spa Deck Stair Wall
(April 9, 2007)


Pool / Spa Deck Stair Wall
(April 9, 2007)


Electrical Service to Cottage
(April 9, 2007)


Curved Palapa Area Retaining Wall
(April 9, 2007)


Curved Palapa Area Retaining Wall
(April 9, 2007)


Pool Equipment Room Floor Reinforcement
(April 9, 2007)


Cottage Utility Trenching
(April 9, 2007)


Electrical Service at Meter Area
(April 9, 2007)


Curved Stairs
(April 9, 2007)


20' Wide Driveway on Lower Plantation Estates Lot
We suggest doing the same due to the steep hillside entry
Currently our plan scales out at 12' wide
(April 9, 2007)


From Street Above
(April 6, 2007)


Setting Large Rafters over Living Room
(April 6, 2007)


Porte Couchere
(April 6, 2007)


Living Room Beams
(April 6, 2007)


Roof Framing above Gym
(April 6, 2007)


Typical Baseboard Outlet
(April 6, 2007)


Spa Deck Area
(April 6, 2007)


Palapa Wall in Foreground, Cottage Beyond
(April 6, 2007)


Cottage
(April 6, 2007)


Electrcial Service from Meter to Cottage
(April 6, 2007)


Electrcial Service from Meter to Cottage
(April 6, 2007)


Underlayment at Porte Couchere
(April 4, 2007)


Garage / Master Suite
(April 4, 2007)


Viewed from Above
(April 4, 2007)


Setting Rafters
(April 4, 2007)


Rough Framing above Corner Dining Room Glass Doors
(April 4, 2007)


Low Garden Wall and Covered BBQ Area
(April 4, 2007)


Living Room
(April 4, 2007)


Upper Hillside
(April 4, 2007)

Previous photos

as of March 29, 2007
as of February 27, 2007
as of December 26, 2006
as of November 30, 2006
as of October 31, 2006
as of September 29, 2006
as of September 12, 2006
as of June 1, 2006
as of April 26, 2006
Design Board Story Pole - September 12, 2005